Q / CSG 510001 — 2015

目 次

前言····································································· ··············Ⅶ
第1 部分 公共规则
1 范围································································ ················ 1
2 规范性引用文件················································· ················ 1
3 术语和定义······················································· ················ 3
4 总则································································ ················ 6
5 作业基本条件及要求··········································· ················ 6
5.1作业保障····················································· ················ 6
5.2作业人员····················································· ················ 6
5.3作业现场····················································· ················ 7
5.4施工电源····················································· ················ 8
5.5灾后抢修····················································· ················ 8
5.6承包商························································ ················ 9
6 保证安全的组织措施··········································· ················ 9
6.1组织措施组成··············································· ················ 9
6.2现场勘察····················································· ·············· 10
6.3工作票组织·················································· ·············· 10
6.4工作票启用·················································· ·············· 17
6.5工作许可····················································· ·············· 18
6.6工作监护····················································· ·············· 22
6.7工作间断····················································· ·············· 22
6.8工作转移····················································· ·············· 23
6.9工作变更和延期············································ ·············· 24
6.10工作终结··················································· ·············· 25
7 保证安全的技术措施··········································· ·············· 26
7.1一般要求····················································· ·············· 26
版权专有 不得翻印 I

Q / CSG 510001 — 2015

7.2 停电·········································································· 26
7.3 验电·········································································· 28
7.4 接地·········································································· 29
7.5 悬挂标示牌和装设遮栏(围栏)······································ 32
8 设 备巡视········································································· 34
8.1 一般要求···································································· 34
8.2 室内巡视···································································· 34
8.3 室外巡视···································································· 34
8.4 线路直升机巡视··························································· 35
9 设 备操作········································································· 35
9.1 操作方式···································································· 35
9.2 操作分类···································································· 36
9.3 操作条件···································································· 36
9.4 操作票······································································· 36
9.5 操作要求···································································· 40
第2 部分 常规作业
10 单 一类型作业································································· 43
10.1 发电机和高压电动机作业············································· 43
10.2 六氟化硫电气设备作业················································ 44
10.3 厂站低压设备作业······················································ 46
10.4 线路融冰作业···························································· 46
10.5 化学品作业······························································· 47
10.6 防止客户侧反送电的措施············································· 48
11 带 电作业······································································· 48
11.1 一般要求·································································· 48
11.2 一般安全技术措施······················································ 49
11.3 等电位作业······························································· 51
11.4 带电断、接引线························································· 53
11.5 带电短接设备···························································· 54
11.6 带电水冲洗······························································· 55
11.7 带电清扫机械作业······················································ 56
II 版权专有 不得翻印

Q / CSG 510001 — 2015

11.8绝缘斗臂车作业·········································· ··············· 56
11.9保护间隙··················································· ··············· 57
11.10带电检测绝缘子········································ ··············· 58
11.11高压配电电缆旁路带电作业························· ··············· 58
11.12高压配电线路带电立、撤杆作业··················· ··············· 59
11.13绝缘平台作业··········································· ··············· 59
12 邻近带电体作业··············································· ··············· 59
12.1一般要求·················································· ··············· 59
12.2感应电压的防护········································· ··············· 59
12.3在带电线路杆塔上的作业······························ ··············· 60
12.4邻近或交叉其他电力线路的作业····················· ··············· 60
12.5同杆塔多回线路中部分线路停电的作业············ ··············· 61
13 二次设备作业·················································· ··············· 62
13.1一般要求·················································· ··············· 62
13.2电流互感器和电压互感器作业························ ··············· 63
13.3现场检修·················································· ··············· 64
13.4整组试验·················································· ··············· 65
14 架空线路作业·················································· ··············· 65
14.1一般要求·················································· ··············· 65
14.2坑洞开挖·················································· ··············· 65
14.3杆塔上作业··············································· ··············· 66
14.4杆塔施工·················································· ··············· 67
14.5放线、紧线与撤线······································· ··············· 68
14.6线路测量·················································· ··············· 70
14.7线路砍剪树木············································ ··············· 70
15 电力电缆作业·················································· ··············· 71
15.1一般要求·················································· ··············· 71
15.2施工安全措施············································ ··············· 71
15.3试验安全措施············································ ··············· 73
16 高、低压配电网作业········································· ··············· 74
16.1一般要求·················································· ··············· 74
16.2高压配电设备作业······································· ··············· 74
版权专有 不得翻印 III

Q / CSG 510001 — 2015

16.3高压配电线路作业······················································ 75
16.4计量、负控装置作业··················································· 76
16.5低压配电网作业························································· 76
第3 部分 专项作业
17 试 验作业······································································· 78
17.1 一般要求·································································· 78
17.2 高压试验·································································· 78
18 电 气测量作业································································· 79
18.1 一般要求·································································· 79
18.2 使用携带型仪器测量··················································· 80
18.3 使用钳形电流表测量··················································· 80
18.4 使用绝缘电阻表测量··················································· 80
18.5 高压线路使用接地电阻表测量······································· 81
18.6 核相作业·································································· 81
18.7 线路工频参数测量······················································ 81
19 水 轮机作业···································································· 81
20 高 处作业······································································· 82
20.1 一般要求·································································· 82
20.2 防高处坠落措施························································· 82
20.3 防高空落物措施························································· 83
20.4 脚手架和高处作业机具················································ 83
20.5 梯子上的高处作业······················································ 83
20.6 特殊天气的高处作业··················································· 84
20.7 阀厅的高处作业························································· 84
21 密 闭空间作业································································· 84
22 水 域作业······································································· 85
22.1 潜水作业·································································· 85
22.2 水面作业·································································· 85
23 焊 接及切割作业······························································ 86
23.1 一般要求·································································· 86
23.2 焊接作业·································································· 86
IV 版权专有 不得翻印

Q / CSG 510001 — 2015

23.3切割作业·················································· ··············· 87
24 动火作业························································ ··············· 88
24.1一般要求·················································· ··············· 88
24.2动火区域和级别········································· ··············· 89
24.3动火工作票··············································· ··············· 89
25 起重与运输····················································· ··············· 92
25.1起重作业一般要求······································· ··············· 92
25.2移动式起重机作业······································· ··············· 94
25.3机动车运输··············································· ··············· 95
25.4非机动车运输············································ ··············· 95
25.5人工运输和装卸········································· ··············· 95
第4 部分 工器具
26 安全工器具····················································· ··············· 97
26.1保管························································ ··············· 97
26.2使用························································ ··············· 97
26.3试验························································ ··············· 99
27 带电作业工具·················································· ··············· 99
27.1保管························································ ··············· 99
27.2使用························································ ·············· 100
27.3试验························································ ·············· 101
28 施工机具························································ ·············· 102
28.1一般要求·················································· ·············· 102
28.2使用························································ ·············· 102
28.3保管、检查和试验······································· ·············· 109
29 电气工具及一般工具········································· ·············· 110
29.1电气工具·················································· ·············· 110
29.2一般工具·················································· ·············· 111
第5 部分 附录
附录A(规范性附录) 安全技术交底单格式··············· ·············· 112
A.1厂站工作安全技术交底单格式························ ·············· 112
版权专有 不得翻印 V

Q / CSG 510001 — 2015

A.2电力线路工作安全技术交底单格式································ 113
附录B(资料性附录)现场勘察记录格式································ 115
附录C(规范性附录) 工作票格式········································· 116
C.1厂站第一种工作票格式··············································· 116
C.2厂站第二种工作票格式··············································· 119
C.3厂站第三种工作票格式··············································· 121
C.4线路第一种工作票格式··············································· 122
C.5线路第二种工作票格式··············································· 125
C.6低压配电网工作票格式··············································· 126
C.7带电作业工作票格式·················································· 128
C.8紧急抢修工作票格式·················································· 129
附录D(规范性附录)工作票附属单格式································ 130
D.1厂站二次设备及回路工作安全技术措施单格式················· 130
D.2分组工作派工单格式·················································· 131
附录E(规范性附录)线路工作接地线使用登记管理表·············· 132
附录F(规范性附录)操作票格式········································· 133
F.1调度逐项操作命令票格式············································· 133
F.2调度综合操作命令票格式············································· 134
F.3现场电气操作票格式··················································· 135
附录G(规范性附录)动火工作票格式···································· 136
G.1一级动火工作票格式·················································· 136
G.2二级动火工作票格式·················································· 138
附录H(规范性附录)安全技术措施标示牌式样······················· 139
附录I(资料性附录)常用起重设备检查和试验周期及质量
参考标准············································ 141
附录J(规范性附录)工器具试验项目、周期和要求················· 143
J.1绝缘安全工器具试验项目、周期和要求··························· 143
J.2高处作业安全用具试验标准·········································· 146
附录K(规范性附录) 绝缘工具电气预防性试验项目及标准········ 148

版权专有 不得翻印

VI

Q / CSG 510001 — 2015

前 言

本规程按照 GB/T 1.1—2009《标准化工作导则 第 1 部分:标准的 结构和编写》给出的规则起草。

本规程根据 GB 26859—2011《电力安全工作规程 电力线路部分》、 GB 26860—2011《电力安全工作规程 发电厂和变电站电气部分》、 DL 5009.2—2013《电力建设安全工作规程 第 2 部分:电力线路》、DL 5009.3—2013《电力建设安全工作规程 第 3 部分:变电站》、DL 408— 1991《电业安全工作规程(发电厂和变电所电气部分)》、DL 409—1991 《电业安全工作规程(电力线路部分)》,结合中国南方电网有限责任公司 (以下简称公司)有关规定编制。

本规程包括五个部分:公共规则、常规作业、专项作业、工器具、附录。 公共规则包括总则,作业基本条件及要求,保证安全的组织措施, 保证安全的技术措施,设备巡视,设备操作等共九章。常规作业包括单 一类型作业,带电作业,邻近带电体作业,二次设备作业,架空线路作 业,电力电缆作业,高、低压配电网作业共七章。专项作业包括试验作 业,电气测量作业,水轮机作业,高处作业,密闭空间作业,水域作业, 焊接及切割作业,动火作业,起重与运输共九章。工器具包括安全工器 具,带电作业工具,施工机具,电气工具及一般工具共四章。

本规程的附录 A、附录 C、附录 D、附录 E、附录 F、附录 G、附录 H、附录 J、附录 K 为规范性附录。

本规程的附录 B、附录 I 为资料性附录。

本规程已经公司 2015 年第一次安委会审议通过,并根据安委会意见 修改完善。

本规程由公司安全监管部负责解释。

本规程主要起草人:许超英、邱野、何朝阳、王超、江北、吴正树、 罗雨、张峰、夏志雄、黄顺发、陈凯华、王科鹏。

本规程为首次发布,自 2015 年 9 月 1 日起实施。公司有关规章、制 度、规定、规范等相关内容均应以本规程为基准。

版权专有 不得翻印 VII

Q / CSG 510001 — 2015

第1 部分 公共规则

1 范围

1.1 本规程规定了公司保障电力工作场所工作人员人身安全和健康的 基本要求。

1.2 本规程适用于公司所属单位,公司境外业务和代管单位参照执行。

2 规范性引用文件

下列文件对于本文件的应用是必不可少的。凡是注日期的引用文件, 仅注日期的版本适用于本文件。凡是不注日期的引用文件,其最新版本(包 括所有的修改单)适用于本文件。

GB/T 156—2007 标准电压

GB 2811—2007 安全帽

GB 2894—2008 安全标志及其使用导则

GB/T 2900.20—1994 电工术语 高压开关设备[IEC 60050(IEV): 1994,NEQ]

GB/T 2900.50—2008 电工术语 发电、输电及配电 通用术语 (IEC 60050—601:1985,MOD)

GB/T 3608—2008 高处作业分级

GB/T 3787—2006 手持式电动工具的管理、使用、检查和维修安全 技术规程

GB/T 5905—2011 起重机 试验规范和程序

GB 6095—2009 安全带

GB/T 6096—2009 安全带测试方法

GB 9448—1999 焊接与切割

GB/T 9465—2008 高空作业车

GB/T 13035—2008 带电作业用绝缘绳索

GB/T 18857—2008 配电线路带电作业技术导则 GB/T 20118—2006 一般用途钢丝绳

版权专有 不得翻印

1

Q / CSG 510001 — 2015

GB 26164.1—2010 电业安全工作规程 第 1 部分:热力和机械 GB/T 28537—2012 高压开关设备和控制设备中六氟化硫(SF6)的 使用和处理

GB 26859—2011 电力安全工作规程 电力线路部分

GB 26860—2011 电力安全工作规程 发电厂和变电站电气部分 GB 26861—2011 电力安全工作规程 高压试验室部分 DL/T 288—2012 架空输电线路直升机巡视技术导则 DL/T 289—2012 架空输电线路直升机巡视作业标志

DL/T 400—2010 500kV 交流紧凑型输电线路带电作业技术导则 DL 408—1991 电业安全工作规程(发电厂和变电所电气部分) DL 409—1991 电业安全工作规程(电力线路部分)

DL/T 596—1996 电力设备预防性试验规程

DL/T 599—2005 城市中低压配电网改造技术导则

DL/T 639—1997 六氟化硫电气设备运行、试验及检修人员安全防

护细则

DL/T 692—2008 电力行业紧急救护技术规范

DL/T 854—2004 带电作业用绝缘斗臂车的保养维护及在使用中的

试验

DL/T 875—2004 输电线路施工机具设计、试验基本要求

DL/T 878—2004 带电作业用绝缘工具试验导则

DL/T 881—2004 ±500kV 直流输电线路带电作业技术导则 DL/T 966—2005 送电线路带电作业技术导则

DL/T 974—2005 带电作业用工具库房

DL/T 976—2005 带电作业工具、装置和设备预防性试验规程 DL/T 1147—2009 电力高处作业防坠器

DL/T 1218—2013 固定式直流融冰装置通用技术条件

DL/T 1242—2013 ±800kV 直流线路带电作业技术规范 DL 5009.2—2013 电力建设安全工作规程 第 2 部分:电力线路 DL 5009.3—2013 电力建设安全工作规程 第 3 部分:变电站 DL 5027—1993 电力设备典型消防规程

JGJ 128—2000 建筑施工门式钢管脚手架安全技术规范 JGJ 130—2001 建筑施工扣件式钢管脚手架安全技术规范