屋面突出结构物及构架模板 安全专项施工方案
屋面突出结构物及构架模板安全专项施工方案.docx
【屋面突出结构物及构架模板安全专项施工方案】
目录
| 一**、编制依据及目的..................................................................................................................................................1** |
|---|
| 1.1 编制依据....................................................................................................................................................................1 |
| 1.2 编制目的....................................................................................................................................................................2 |
| 二**、工程概况.............................................................................................................................................................2** |
| 2.1 项目简介....................................................................................................................................................................2 |
| 2.2 突出屋面结构工程概况............................................................................................................................................3 |
| 2.3 施工重点难点分析及应对措施................................................................................................................................4 |
| 三**、施工准备.............................................................................................................................................................5** |
| 3.1 技术准备....................................................................................................................................................................5 |
| 3.2 资源配置计划............................................................................................................................................................5 |
| 四**、主要施工方法及措施...........................................................................................................................................6** |
| 4.1 模架施工....................................................................................................................................................................6 |
| 4.2 钢筋施工..................................................................................................................................................................13 |
| 4.3 混凝土施工..............................................................................................................................................................13 |
| 4.4 外架施工..................................................................................................................................................................14 |
| 五**、施工安全保证措施.............................................................................................................................................14** |
| 5.1 构配件材料吊运措施..............................................................................................................................................14 |
| 5.2 模板及支架在安装阶段的保证措施......................................................................................................................14 |
| 5.3 水平及临边防护措施..............................................................................................................................................15 |
| 5.4 用电防火与防雷接地措施......................................................................................................................................16 |
| 5.5 混凝土浇筑阶段的保证措施..................................................................................................................................16 |
| 5.6 监测监控措施.........................................................................................................................................................17 |
| 5.7 模板及支撑架拆除阶段的保证措施......................................................................................................................19 |
| ※5.8 施工安全管理......................................................................................................................................................20 |
| 六**、质量要求及管理措施.........................................................................................................................................20** |
| 6.1 质量要求及验收......................................................................................................................................................20 |
| 6.2 模板施工质量通病防治及保证措施......................................................................................................................22 |
| 七**、绿色施工............................................................................................................................................................24** |
| 八**、应急预案............................................................................................................................................................25** |
【屋面突出结构物及构架模板安全专项施工方案】
| 8.1 应急预案的目的......................................................................................................................................................25 |
|---|
| 8.2 事故的应急管理体系..............................................................................................................................................25 |
| 8.3 应急预警及信息报告..............................................................................................................................................27 |
| 8.4 应急物资和设备准备..............................................................................................................................................27 |
| 8.5 重大事件、危险源的辨识......................................................................................................................................28 |
| 8.6 主要危险源预防措施..............................................................................................................................................28 |
| 8.7 应急保障措施..........................................................................................................................................................29 |
| 8.8 应急救援路线图......................................................................................................................................................30 |
| 九**、计算书...............................................................................................................................................................30** |
| 9.1 300×700MM梁底模支撑架计算书(扣件式).....................................................................................................30 |
| 9.2 600×1000MM梁底模板支架计算书(扣件式)......................................................................................................42 |
| 9.3 梁侧模板计算书......................................................................................................................................................51 |
| 9.4柱模板支撑计算书....................................................................................................................................................56 |
| 十**、附件...................................................................................................................................................................63** |
| 10.1专职安全生产管理人员及特种作业人员证件......................................................................................................63 |
| 10.2 方案附图................................................................................................................................................................64 |
【屋面突出结构物及构架模板安全专项施工方案】
一、编制依据及目的
1.1 编制依据
1.1.1 主要规范规程
| 序号 | 名称 | 编号 | 类别 |
|---|---|---|---|
| 1 | 混凝土结构设计规范 | GB 50010-2010 | 国家 |
| 2 | 建筑结构荷载规范 | GB 50009-2012 | 国家 |
| 3 | 混凝土结构加固设计规范 | GB 50367-2013 | 国家 |
| 4 | 建筑施工安全技术统一规范 | GB 50870-2013 | 国家 |
| 5 | 工程测量规范 | GB 50026-2007 | 国家 |
| 6 | 混凝土结构工程施工质量验收规范 | GB 50204-2002 | 国家 |
| 7 | 建筑工程施工质量验收统一标准 | GB 50300-2001 | 国家 |
| 8 | 建筑施工脚手架安全技术统一标准 | GB 51210-2016 | 国家 |
| 9 | 安全网 | GB 5725-2009 | 国家 |
| 10 | 建筑施工脚手架安全技术统一标准 | GB 51210-2016 | 国家 |
| 11 | 施工现场消防安全技术规程 | GB 50720-2011 | 国家 |
| 12 | 钢筋机械连接通用规程 | JGJ 107-2016 | 行业 |
| 13 | 钢筋焊接及验收规程 | JGJ 18-2012 | 行业 |
| 14 | 混凝土结构后锚固技术规程 | JGJ 145-2013 | 行业 |
| 15 | 建筑施工扣件式钢管脚手架安全技术规范 | JGJ 130-2011 | 行业 |
| 16 | 建筑施工高处作业安全技术规范 | JGJ 80-2016 | 行业 |
| 17 | 建筑施工承插型盘扣式钢管支架安全技术规程 | JGJ 231-2010 | 行业 |
| 18 | 建筑机械使用安全技术规程 | JGJ 33-2012 | 行业 |
| 19 | 施工现场临时用电安全技术规范 | JGJ 46-2005 | 行业 |
| 20 | 建筑施工安全检查标准 | JGJ 59-2011 | 行业 |
| 21 | 深圳市建设工程安全文明施工标准 | SJG-46-2018 | 地方 |
第 1 页共 64 页
【屋面突出结构物及构架模板安全专项施工方案】
1.1.2 安全管理法律法规
| 序号 | 名称 | 编号 |
|---|---|---|
| 1 | 建筑安全生产监督管理规定 | 建设部令第13号 |
| 2 | 建设工程施工现场管理规定 | 建设部令第15号 |
| 3 | 危险性较大的分部分项工程安全管理办法 | 建设部【2018】37号 |
| 4 | 关于实施《危险性较大的分部分项工程安全管理规定》有 关问题的通知 |
建办质〔2018〕31号 |
| 5 | 住房城乡建设部办公厅关于进一步加强危险性较大的分 部分项工程安全管理的通知 |
住建部建办质[2017]39号 |
| 6 | 大型工程技术风险控制要点 | 建质函[2018]28号 |
| 7 | 关于进一步加强房屋市政工程脚手架支撑体系使用的钢 管扣件等构配件管理的通知 |
粤建质函[2011]796号 |
| 8 | 广东省住房和城乡建设厅关于印发房屋市政工程危险性 较大的分部分项工程安全管理实施细则的通知 |
粤建规范[2019]2号文 |
| 9 | 深圳市住房和建设局关于发布《深圳市建设工程安全文明 施工十项标准(试行)》、《深圳市建设工程安全文明施工 十项禁令》的通知 |
深建质安[2017]112号 |
| 10 | 关于进一步加强建筑起重机械及吊装作业安全管理的通 知(试行) |
深建质监[2018]10号文 |
| 11 | 深圳经济特区建设工程施工安全条例 | 深圳市人大常委会第60号 |
| 12 | 深圳经济特区建设项目环境保护条例 | 深圳市人大常委会第24号 |
| 13 | 深圳市扬尘污染防治管理办法 | 深圳市人民政府令第187号 |
1.1.3 图纸、施工组织设计及其他资料
| 序号 | 名称 | 编号 |
|---|---|---|
| 1 | 建筑及结构施工图 | / |
| 2 | 施工组织设计 | / |
1.2 编制目的
本工程突出屋面结构均未施工,为贯彻《深圳市住房和建设局文件:深建质安[2020]111 号》文关于深圳市住房和建设局转发关于进一步加强屋面突出结构物及其他现浇装饰构架施 工安全管理的紧急通知,针对本工程尚未施工的突出屋面结构,为满足安全施工要求,特编
第 2 页共 64 页
【屋面突出结构物及构架模板安全专项施工方案】
制本方案。
二、工程概况
2.1 项目简介
本工程位于南山前海深港合作区核心地段,由T7、T8两栋办公楼组成,地下室5层,
T7、T8办公楼塔楼分别为18层、27层;裙楼为3层;总建筑面积 124972.01 ㎡,主要建筑功能
为办公和商业。
| 工程名称 | / | |
|---|---|---|
| 建设单位 | / | |
| 设计单位 | / | / |
| 监理单位 | / | |
| 施工单位 | / | |
| 工程地址 | / |
2.2 突出屋面结构工程概况
T7栋屋面层以上共两层结构,其中核心筒区域为机房及电梯井等,塔楼外框为花架;T8 栋屋面层以上共两层结构,其中核心筒区域为机房及电梯井等,非核心筒区域为花架及擦窗 机轨道。
T7、T8塔楼屋面以上均有2层突出结构物及构架梁(屋面突出结构物及其他现浇装饰构架 包括:突出屋面的现浇电梯间、楼梯间、水箱间、设备间、装饰构架、悬挑构架、独立的构 筑物,及其他不便形成纵横向满堂架的现浇结构), 电梯间及楼梯间梁截面尺寸:400× 600mm、400×800mm、400×1000mm、500×800mm、600×1000mm,突出结构物≤4.5m,部分结构 物有板,板厚≤150mm。
花架梁尺寸包括:T7: 750×500mm、700×500mm、600×500mm,第一层层高为3.7m,第二 层层高为5.1m;T8: 700×900mm、600×900mm、600×800mm、800×800mm、 800×900mm、800×
1050mm、700×1050mm,第一层层高为4.75m,第二层层高为3.65m。
擦窗机轨道梁尺寸:600×800mm,层高4.75m。
第 3 页共 64 页
【屋面突出结构物及构架模板安全专项施工方案】
T7栋出屋面层(83.550标高)结构平面布置图 T7栋屋顶层(88.650m标高)结构平面布置图
T8栋办公楼出屋面层结构布置图 T8栋办公楼屋顶层结构布置图
2.3 施工重点难点分析及应对措施
T7、T8屋面层以上结构由原来的钢结构变更为型钢混凝土结构,大大提升了施工难度,
其施工重点难点及应对措施如下表所示:
| 序号 | 施工内容 | 重点难点 | 应对措施 |
|---|---|---|---|
| 1 | 混凝土结构施工 | 架空层梁、柱结构钢筋绑扎 | 满堂架搭设操作平台,架空区域无法使用布 |
第 4 页共 64 页
【屋面突出结构物及构架模板安全专项施工方案】
| 及混凝土浇筑施工困难 | 料机,混凝土浇筑时泵管接至架空梁面标高 | ||
|---|---|---|---|
| 后,再接软管进行梁柱混凝土浇筑。 | |||
| 2 | 模板架体 | 架空层梁、柱结构模架搭设 较为困难 |
塔楼边梁处采用扣件钢管架搭设,高宽比为 1:1,非塔楼边梁区域采用盘扣架搭设。 |
三、施工准备
3.1 技术准备
- 1 、 施工前编制详细的安全专项施工方案,方案报公司审核,由公司总工程师审批,细化
修改后组织专家论证,方案按照专家论证意见修改完成后报监理审批 。
| 姓名 | 学历 | 专业 | 职务 | 职称 | |
|---|---|---|---|---|---|
| 方案审批 | 周予启 | 研究生 | / | 公司总工 | 高级工程师 |
| 方案审核 | 宋欢 | 本科 | 土木工程 | 项目总工 | 工程师 |
| 方案编制 | 王静 | 本科 | 工程力学 | 方案师 | / |
2 、 施工前由总工程师对项目管理人员 、 分包管理人员及作业人员进行方案的安全技术交
底,交底应全面细致,要求现场施工严格按方案执行 。
3 、 工人进场后做好三级安全教育,提高工人的安全防范意识 。
4 、 施工前认真查阅图纸(包括与建筑图对应情况),做好图纸审查记录 、 设计变更洽商记
录 、 设计交底记录,找出模板及模板支撑架工程中施工重难点 、 注意事项等,做到施工中重点
突出 。
5 、做好模板及模板支架施工的技术资料和施工过程中的检验记录,并及时收集和整理上
述资料,以保证技术资料的及时、准确、完整。
- 6、 混凝土浇筑前,必须仔细查看图纸,对浇筑部位 、 浇筑方法 、 浇筑路线 、 相关的质量
要求 、 安全要求等做详细的安全技术交底,待相关工序验收合格后申报混凝土浇灌令,并落
实浇筑人员,正确分工,责任到人 。
7、 检查模板的轴线位置 、 截面尺寸 、 标高 、 垂直度 、 支撑的牢固程度及模板拼缝的严密
- 第 5 页共 64 页
【屋面突出结构物及构架模板安全专项施工方案】
程度,确保模板内的杂物和钢筋上的油污已经清理干净,对钢筋保护层 、 预埋件和预留洞进
行检查,做好模板和钢筋的验收工作 。
3.2 资源配置计划
1、施工机具准备
科学配置机械设备是确保计划完成的重要条件。针对机械设备的配置原则:设备先进、
性能优良、环保节能、数量充足。
2、物资
主要材料计划
| 序号 | 材料名称 | 型号/规格 | 用途 |
|---|---|---|---|
| 1 | 扣件式钢管 | Φ48.3×3.6 | 搭设支撑架、模板龙骨 |
| 3 | 直角扣件 | 与Φ48钢管配套 | 搭设支撑架 |
| 4 | 旋转扣件 | 与Φ48钢管配套 | 搭设支撑架 |
| 5 | 对接扣件 | 与Φ48钢管配套 | 搭设支撑架 |
| 6 | 可调托撑 | Φ36 | 搭设支撑架 |
| 7 | 立杆(盘扣架) | Φ48×3.2mm | 搭设支撑架 |
| 8 | 水平杆(盘扣架) | Φ42×2.5mm | 搭设支撑架 |
| 9 | 水平安全网 | 大眼网 | 安全防护(宿舍大堂) |
| 10 | 木龙骨 | 50×100mm | 模板龙骨 |
| 11 | 覆膜木胶合板 | 915183015mm | 搭设模板 |
| 12 | T14 普通对拉螺杆(通 | Φ14 | / |
丝)
备注:1)以上所列材料用量为估算量,具体应以现场实际情况为准;
施工人力安排计划表
| 序号 | 工种名称 | 人数(人) | 工作内容 |
|---|---|---|---|
| 1 | 钢筋工 | 30 | 钢筋加工、安装 |
第 6 页共 64 页
【屋面突出结构物及构架模板安全专项施工方案】
| 序号 | 工种名称 | 人数(人) | 工作内容 |
|---|---|---|---|
| 2 | 木工 | 25 | 模架体系加工、安装等 |
| 3 | 混凝土工 | 20 | 混凝土浇筑、养护 |
| 4 | 架子工 | 30 | 外架、支撑架搭设及拆除 |
| 5 | 焊工 | 20 | 焊接 |
| 6 | 塔吊司机信号工 | 2 | 垂直运输 |
四、主要施工方法及措施
4.1 模架施工
突出屋面的现浇电梯间、楼梯间等模板支撑系统采用盘扣式钢管满堂脚手架;擦窗机轨 道及构架梁下模板支撑体系采用扣件式满堂架,且高宽比不大于1:1,模架布置详见附图。
1、擦窗机轨道及构架梁(扣件)
| 部位 | 梁底 | 梁侧 |
|---|---|---|
| 模板 | 15厚 | 多层板 |
| 支撑架 | 扣件式钢管支撑架(满堂 | 架,高宽比不得大于1:1) |
| / | 设置1道M14对拉螺杆 | |
| 主龙骨 (双Ф48钢管) |
≤0.9m | 纵向:≤450mm 竖向:≤450mm |
| 次龙骨 (50×100木方) |
①类梁(截面积S≤0.21㎡):梁下木 (截面积0.21㎡<S≤0.84㎡): |
方平行于梁截面布置间距250,②类梁 梁底木方平行于梁截面布置间距200 |
| 梁板分类支撑方法 | 梁截面≤0.21m2,梁下木方平行于梁截 杆,横距900,纵距≤900,主楞单钢 梁底设1根立杆,方楞双钢管,立杆顶 为验算对象。②类梁(截面积0.21 m2 布置间距200,梁下每排设2根承重立 钢管主楞,以600×1000梁为验算对象 架梁下之间的镂空处搭设满堂架,立 构架梁纵距一致且拉结成整体)。 |
面布置间距250,梁下每排设2根承重立 管,双扣件节点(当梁宽不大于400时, 设可调托撑,纵距900),以300×700梁 <S≤0.84 m2):梁底木方平行于梁截面 杆,横距600,纵距900,可调托撑内双 。构架支模体系的高宽比应控制≤1,构 杆纵横向间距不大于900×1000(与相邻 |
| 剪刀撑 | 纵、横向每5跨(且不大于5m),由底 设置设置连续剪刀撑。剪刀撑宽度应 置连续水平剪刀撑。梁、板支架立杆 撑应相互连通、连接并形成整体,以 外脚手架及电梯井操作架作为现浇构 |
至顶设置连续竖向剪刀撑,架体外立面 为5跨。在竖向剪刀撑顶部交点平面应设 上的纵横水平杆、扫地杆、斜杆和剪刀 保证支撑体系的整体稳定性,严禁借用 件的支模承重杆件。 |